Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Euston station
- Contractor
- Network Rail (Euston)
- Type of works
- scaffold works
- Estimated Start Date
- 14/10/2023
- Estimated End Date
- 10/12/2023
What we are doing
Network Rail improvement works above Euston Station platforms 12-16
Between 08:30 on the 14 October and 03:00 on the 16 October Skanska will be continuing work above platforms 12-16 on the “Parcel Deck” this involves scaffolding work and some more work to the steel façade (steel wall/face). Whilst we don’t anticipate this work to be especially noisy, we wanted to make to you aware that it is taking place.
There will also be work on the following dates.
- 21 October 21:00 to 22 October 12:00 – Scaffold work, steel façade installation.
- 2 December 21:00 to 3 December 12:00 – Scaffold work, steel façade installation.
- 9 December 21:00 to 10 December 12:00 – Scaffold work, steel façade installation, fabric screen installation.
For further details of works please see notification below.