Eversholt Street 16” water main replacement work including bus diversion
Work item: Thames Water 7001118
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Camden, Euston station
- Contractor
- Mace Dragados JV, Thames Water
- Type of works
- Traffic management, Utility works / surveys
- Estimated Start Date
- 01/03/2021
- Estimated End Date
- 31/07/2021
What we are doing
Thames Water will be replacing the 16” water main on Eversholt Street during the first half of 2021.
The work will begin in early January and will take several months to complete. Thames Water is working closely with HS2, the London Borough of Camden and TfL to ensure that the least amount of disruption is caused to residents, businesses and road users while this essential work is taking place.
For further information and any queries about these works, please contact Thames Water on 0800 316 9800 and quote bulletin board number 70011180.
Download information relating to these works
- 20 May 2021: Eversholt Street Thames Water Update
- 26 February 2021: Eversholt Street Thames Water Update #5
- Bus stop alternatives - Eversholt Street