Expansion of works area at Ruislip Golf Course

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-14-8/6/21

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
Breakspear Road South
Contractor
SCS JV
Type of works
Worksite / compound set-up
Estimated Start Date
23/08/2021
Estimated End Date
12/09/2021

What we are doing

What we are doing
Our works have now progressed to the point where we need to occupy additional land to facilitate works on the railway. This area is shown on the map below and is to the north of the current hoarding line. This area will allow us to fully build the internal haul road and Stockpile essential materials for these works.