Extended hours at our sites on Harvil Road and Newyears Green Lane – Showing locations near Harvil Road

Work item: HS2-EW-SCS-Ph1-Ca-S1-Prog-works-50-17/06/2021

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
Harvil Road, Newyears Green Lane
Contractor
SCS JV
Type of works
Early construction works, Extended working hours
Estimated Start Date
07/07/2021
Estimated End Date
31/10/2021

What we are doing

Extended working hours within our sites
Works are ongoing at our sites at Harvil Road and Newyears Green Lane to build the new road realignment, the Copthall Tunnels and the conveyor system. Some of these works will need to take place during extended working hours.

From 7 July until 31 October 2021, we will be extending our working hours on our sites and will be undertaking work on site from 7am to 6pm, Monday through Saturday. This is an extension of our core working hours of 8am to 6pm Monday to Friday and 8pm to 1pm on Saturdays.

We will only carry out activities agreed with the London Borough of Hillingdon and will adhere to the agreed working hours, noise and vibration limits.

We will continue to monitor noise, dust and vibration throughout our works to ensure that we have adequate measures in place to minimise disruption.  We appreciate your continued patience while we build HS2.

Please see the following pages for more information about the works we will
be carrying out during this period.

Activities
Copthall Tunnel preparation work
This activity covers the excavation from the pile platform level to the formation level of the bridge, including bored piling works.

Installation of Conveyor
This activity covers the installation of the conveyor system at Newyears Green Lane, allowing us to move soil to the Northern Sustainable Placement area.

Harvil Road over the Chiltern line Bridge
This activity covers the preparation work for the new bridge, in addition to the north and south abutments of the Chiltern Line. This will include the following activities: placement of concrete blinding on the formation, reinforcement fixing, installation of formwork and shuttering, pouring of concrete for the foundation and abutment.

Harvil Road realignment embankment construction
This activity is the construction and build-up of embankments for the realignment of Harvil Road. This activity will commence after the completion of the temporary road diversion.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]