Extended hours concrete pour at Granby Terrace bridge – 7 May

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-1-23/04/2025

Work Item Summary

Project Phase
Phase 1
Location
Granby Terrace bridge
Worksite Name
Euston Approaches
Contractor
SCS JV
Type of works
Concrete pours
Estimated Start Date
07/05/2025
Estimated End Date
07/05/2025

What we are doing

We are continuing our work to construct the new bridge deck for Granby Terrace bridge. We completed the main bridge deck in November 2024 and are now constructing the northern roof slab and other supporting structures.

As part of this work, we completed the first large concrete pour on 1 April. We now need to complete the second pour on 7 May. The works are weather dependent, and if we are unable to complete the pour on this day, we will carry out this work on Tuesday 13 May.

Once we begin pouring concrete for a slab, we must continue until it is finished. We will prepare our working area the day before so we can begin pouring concrete at 7am on the day. We plan to finish by 6pm, however if there are any delays, we may finish later than this. We will not carry out any noisy works until after 8am.

We will have approximately 70 wagons delivering concrete to our site. To reduce the impact of this, concrete wagons will access the worksite through our site gate on Hampstead Road.

You may notice periods of noise from the concrete pour and additional lorries throughout the day. We are sorry for any disruption this work might cause.

For further details please follow the link to the notification below.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]