Extended hours working in Camden Cutting north – week commencing 4 December
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-01/12/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Camden Cutting north
- Worksite Name
- Euston Approaches
- Contractor
- SCS JV
- Type of works
- Concrete pours, Delivery of materials
- Estimated Start Date
- 04/12/2023
- Estimated End Date
- 08/12/2023
What we are doing
We are currently working at track-level to construct the base for the Euston Cavern headhouse, close to 1 Park Village East.
We previously informed you we would carry out a large concrete pour in Camden Cutting north on Wednesday 29 November, however we were unable to do so.
We now plan to complete this pour on Thursday 7 December. The works are weather dependent, and we will consider other days during that week if necessary. If we are unable to complete the pour that week, we will look to do it in mid-December.
Once we begin pouring concrete for a slab, we must continue until it is finished. Sometimes this means pouring concrete during extended working hours. We will be onsite from 6am to prepare our working area. We will start works at 7am and plan to finish by 11pm. We will have around 70 wagons delivering concrete to our site.
You may notice periods of noise from the concrete pour and additional lorries on Park Village East throughout the day. To reduce the impact, concrete wagons will access site via our site gate on Hampstead Road and the lorry lay-by at the northern end of Park Village East.
We are sorry for any disruption this work might cause.
For further details of above and other weekend works in Euston Approaches please see notification below.
Download information relating to these works