Extended working hours at Greenford Road

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-UT-1-30/05/2024

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Greenford Road
Worksite Name
Greenpark Way
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
06/06/2024
Estimated End Date
31/07/2024

What we are doing

We wrote to you in May to let you know that our utility works on Greenford Road will be ongoing until late July 2024.

In order to complete these works as soon as we can, from 6 June, we may on occasion need to work extended hours. On certain days, we may start work at 7am instead of 8am, and works may overrun until 10pm. This will not be every day.

The works during the extended hours are not expected to be noisy.

Consent to work these extended hours has been given by Ealing Council.

We apologise for any inconvenience these extended working hours may cause.