Extended working hours at our site on Breakspear Road South
Work item: S2-EW-SCS-Ph1-Ar-So-S2-Prog-works-1-31/05/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Breakspear Road South
- Worksite Name
- Breakspear Road South
- Contractor
- SCS JV
- Type of works
- Construction
- Estimated Start Date
- 17/06/2024
- Estimated End Date
- 31/12/2024
What we are doing
From 17 June to 31 December 2024, we will be carrying out work at our site on Breakspear Road South, north of the Chiltern Railway Line, either side of Breakspear Road South.
We will be working to construct the three Retained Embankments that connect the West Ruislip Portal, east of our site to the Copthall Tunnel, which is west of our site boundary. The consented extended working hours are, 7am to 7pm Monday to Friday and 7am to 4pm on Saturdays.
We will be building the Embankments to required height using machinery for delivery and placement of material and the compaction of placed material, including vibratory rollers.
We expect that these works will create some noise; however, we will ensure that the noisy works will not commence before 8am, including the use of ground compaction equipment, and excavator activities.
We will only carry out activities agreed with the London Borough of Hillingdon and will adhere to the agreed working hours, noise and vibration limits.
Every effort is being taken to ensure that these works are carried out in the least impactful way. We will ensure that disruption is kept to a minimum.