Extended working hours at the Atlas Road site
Work item: Reference number: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-1-24/03/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Atlas Road
- Worksite Name
- Old Oak Common
- Contractor
- SCS JV
- Type of works
- Extended working hours
- Estimated Start Date
- 30/03/2022
- Estimated End Date
- 09/06/2022
What we are doing
Extended working hours at Atlas Road site
Works are continuing on site to construct the Atlas Road Logistic Tunnel ramp and launch box in preparation for the launch of the tunnel boring machine later in the year.
We are now reaching the stage where we will need to commence with a series of large concrete pours and curing to complete the ramp leading to the launch box. The concrete pours need to take place continuously.
From 30 March to 9 June 2022, we may need to extend our working hours from 8am to 8pm Monday to Friday. We will not be working extended hours every day, but may need to work extended hours on the dates the concrete pours are planned, as follows:
• 30 March 2022
• 20 April 2022
• 6 May 2022
• 9 May 2022
• 20 May 2022
• 7 June 2022
• 9 June 2022
Please note these dates may change by +/- 1 day throughout the period stated above.