Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Site-1-05/02/2024

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Granby Terrace bridge
Worksite Name
Euston Approaches
Contractor
SCS JV
Type of works
Concrete pours
Estimated Start Date
22/02/2024
Estimated End Date
22/02/2024

What we are doing

We are currently working to construct a large retaining wall in front of Regent’s Park estate. This wall, which extends from Granby Terrace to Hampstead Road, will form the side of the new HS2 railway cutting.

As part of this work, we will need to complete a large concrete pour.

Weather permitting, we plan to complete this pour on Tuesday 22 February.