Extension to utility works on Adelaide Road
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-04/07/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Adelaide Road
- Worksite Name
- Adelaide Road
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 05/07/2023
- Estimated End Date
- 25/07/2023
What we are doing
UK Power Networks are currently installing electricity cables on Adelaide Road. A letter was sent to residents directly from UK Power Networks in late May explaining the works, and that they were due to be complete on 30 June.
Works in the lane outside 74 Adelaide Road now need to continue until Tuesday 25 July. The lane is partially closed, with temporary traffic lights in place. The driveways in front on 74 Adelaide Road will be inaccessible until Friday 7 July. Alternative parking provisions have been provided.
From 13 to 25 July the work will continue on the pavement outside 76 Adelaide Road. A pedestrian diversion and temporary traffic lights will be in place.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]