Footway closure on Prince Albert Road

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Site-1-29/07/2022

Work Item Summary

Project Phase
Phase 1
Location
Prince Albert Road
Worksite Name
Vehicle Holding Area
Contractor
SCS JV
Type of works
Delivery of materials, Footpath closures, Worksite / compound set-up
Estimated Start Date
15/08/2022
Estimated End Date
10/09/2022

What we are doing

Site maintenance at the Vehicle Holding Area

Over the next few months, we will carry out a range of site maintenance at the Vehicle Holding Area including removing some of the temporary welfare cabins and finishing works to the entrance.

Extended hour working – Saturday 17 September

For safety, we will lift and remove the temporary cabins during the weekend when there are less people and vehicles on site. We will work Saturday 10 September, 8am to 5pm, to clear and disconnect the cabins before using a crane to lift them onto lorries. The crane will be delivered to site early Friday morning, and removed Saturday evening.

The main welfare building will remain as is. We don’t expect these works to be noisy.