Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Site-1-29/07/2022
Work Item Summary
- Project Phase
- Phase 1
- Location
- Prince Albert Road
- Worksite Name
- Vehicle Holding Area
- Contractor
- SCS JV
- Type of works
- Delivery of materials, Footpath closures, Worksite / compound set-up
- Estimated Start Date
- 15/08/2022
- Estimated End Date
- 10/09/2022
What we are doing
Site maintenance at the Vehicle Holding Area
Over the next few months, we will carry out a range of site maintenance at the Vehicle Holding Area including removing some of the temporary welfare cabins and finishing works to the entrance.
Extended hour working – Saturday 17 September
For safety, we will lift and remove the temporary cabins during the weekend when there are less people and vehicles on site. We will work Saturday 10 September, 8am to 5pm, to clear and disconnect the cabins before using a crane to lift them onto lorries. The crane will be delivered to site early Friday morning, and removed Saturday evening.
The main welfare building will remain as is. We don’t expect these works to be noisy.