Further works on Adelaide Road site boundary

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-33-03/05/2021

Work Item Summary

Project Phase
Phase 1
Region
Camden, London
Location
Camden
Contractor
SCS JV
Type of works
Construction, Traffic management, Worksite / compound set-up
Estimated Start Date
15/03/2021
Estimated End Date
30/06/2021

What we are doing

Further works on the Adelaide Road site boundary

From mid-March until late-June 2021, we will be carrying out essential works to continue setting up our Adelaide Road site boundary. These works
include:

  • Gates installation
  • Site access ramp
  • Installation of bulk timbers on the hoarding
  • Hoarding lighting

Temporary traffic management on Adelaide Road

To carry out these works safely, we will require five short, temporary lane
closures next to our site. The works will be carried out in five phases and we
will use temporary traffic lights to minimise disruption to local residents and
road users.