Gas main trial hole surveys on Drummond Street
Work item: HS2-MW-MD-Ph1-Eu-St-S3-Prog-works-15-23/08/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden, London
- Location
- Drummond Street
- Contractor
- Mace Dragados JV
- Type of works
- Survey
- Estimated Start Date
- 01/09/2022
- Estimated End Date
- 31/10/2022
What we are doing
Gas main trial hole surveys on Drummond Street from September to October 2022
We will be carrying out utilities works to the west of Euston station. As part of this, we will be carrying out gas trial hole surveys on Drummond Street from September to October 2022. This is required to ascertain the condition of the existing gas main at the point where a future new permanent gas main will be connected.
The surveys will be to the south and north side of Drummond Street and will be carried out in succession, i.e. south trial hole survey followed by north trial hole survey. It is anticipated that each survey will take approximately 1-2 weeks. Drummond Street will continue to remain open.
Please notification for details of works locations and traffic management.