Greenford Road reinstatement works

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-06/12/2024

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing, London
Location
Greenford Road
Contractor
SCS JV
Type of works
Traffic management
Estimated Start Date
20/01/2025
Estimated End Date
27/01/2025

What we are doing

From 20 to 27 January 2025 we will be carrying out road and footpath reinstatement works on Greenford Road and Bennetts Avenue, Greenford.

From 20 to 23 January 2025, we will replace the gas covers on Greenford Road and grout the kerb and footpath slabs. On Bennetts Avenue we will replace some asphalt on the footpath and repaint the yellow lines. This work will take place between 8am to 6pm.

There will be a narrowed lane and footpath along Greenford Road with traffic and pedestrian access maintained in both directions. There will be a road closure on Bennetts Avenue at the junction with Greenford Road. For access to Bennetts Avenue from Greenford Road, traffic will be diverted towards Downing Drive and up Middleton Avenue.

From 24 to 27 January 2025, we will be carrying out footpath repair works on Greenford Road close to Rockware Avenue. We will be using a vacuum excavator to dig up the footpath. Noise reducing barriers will be in place where possible to help minimise disruption. There will be a lane and footpath closure with four-way temporary traffic lights during these works. A clearly signposted pedestrian diversion will be in place.

We will be working extended hours in agreement with Ealing Council:
• Friday 24 January, Saturday 25 January – 8am to 8pm
• Sunday 26 January – 8am to 6pm
• Monday 27 January – 8am to 8pm

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]