Ground investigation to the south of Peacock Lane
Work item: HS2 EW BBV Ph2b Prog works 23 19/07/2021
Work Item Summary
- Project Phase
- Phase 2b
- Region
- Manchester
- Location
- High Legh
- Worksite Name
- Peacock Lane
- Contractor
- Balfour Beatty
- Type of works
- Ground investigations
- Estimated Start Date
- 02/08/2021
- Estimated End Date
- 27/08/2021
What we are doing
Ground investigations works are being carried out to help us better understand the ground conditions along the route to inform the detailed design of the railway.
The ground investigation techniques that will be used on this project will primarily include the drilling of boreholes, trial pits and cone penetration tests.