Ground investigation works on the B4118 Birmingham Road , Water Orton
Work item: HS2-MW-Ph1-Ar-No-N2-Traf-2-18/11/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Water Orton
- Contractor
- National Grid
- Type of works
- Ground investigations
- Estimated Start Date
- 14/12/2022
- Estimated End Date
- 21/12/2022
What we are doing
NGED (National Grid Electrical Distribution) are undertaking non-intrusive ground investigation works along a 700 metre section of the B4118 Birmingham Road. The section along which work will be undertaken is shown in red on the map on page 2. In order to carry out the work safely, traffic management measures (temporary two-way traffic lights) will be in place for the duration of the works. Access to all properties will be maintained at all times.
The work is planned to start on 14 December 2022 and is expected to last until 21 December 2022. All of the works will be undertaken between the hours of 9:30am to 3:30pm each weekday. The temporary traffic lights will be removed outside those hours.