Update: Hampstead Road utility diversion works – north

Work item: HS2-SCS-25-1227

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Hampstead Road
Contractor
SCS JV
Type of works
Utility Works
Estimated Start Date
21/10/2025
Estimated End Date
23/12/2025

What we are doing

Following our site safety stand down, we have now begun a safe restart of works across our sites in Euston Approaches. From 21 October to 23 December we will continue our utility diversion works within the northbound outside lane on Hampstead Road near Granby Terrace bridge.

From 3 to 28 November, in addition to the outside northbound lane closure, we will close one outside southbound lane on Hampstead Road.

We will also dig a trial hole in the eastern footpath on Hampstead Road.We will partially close the footpath and divert pedestrians up and around the closure to maintain access to Ampthill Estate. We will hand dig, survey, and then reinstate the area.

There may be some periods of increased noise as we complete this work. We will continue to monitor the traffic management and reduce impacts where possible. We apologise for any inconvenience caused.

HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]