HS2 Works Notification: Update overnight surveys on Springfield Lane, West End Lane and Kilburn Place

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-1-14/10/2021

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Kilburn
Worksite Name
Canterbury Works
Contractor
SCS JV
Type of works
Survey
Estimated Start Date
29/10/2021
Estimated End Date
03/11/2021

What we are doing

Additional utility surveys in your area

We recently wrote to you regarding drainage surveys on Springfield Lane, Kilburn Priory and Langtry Road from 25 to 28 October 2021.

Our previous notification mentioned that we would carry out further surveys in the area during November. The additional surveys are now confirmed and will take place on Springfield Lane from 29 October to 3 November. During these dates we will also carry out surveys on West End Lane at the junction with Kilburn Place.

We will investigate the condition of the sewer system using a camera and may need to flush the system if any blockages are found. Your utility services will not be affected during these works.

Overnight surveys on Springfield Lane and West End Lane

We are planning to carry out overnight drainage surveys during the following dates and time:
• 29 October overnight between 9pm and 6am
• 1 November overnight between 9pm and 6am
• 2 November overnight between 9pm and 6am
• 3 November overnight between 9pm and 6am

Temporary changes will be in place on Springfield Lane and West End Road during the surveys. More information is included on the next page.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]