HS2: Aylesbury Newsletter, December 2021
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Prog-works-49-07/10/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- A41, Aylesbury
- Contractor
- EKFB JV
- Estimated Start Date
- 16/12/2021
- Estimated End Date
- 30/06/2022
What we are doing
Over the next couple of months, you can expect to see the following works in the local area;
• Ground Investigation (GI), topography and survey works;
• Utility works including trial holes;
• UKPN utility connection works around our compound areas
• CCTV drainage works
• Princes Risborough to Aylesbury Railway overnight deliveries;
• Greenway Pedestrian Crossing;
• Test piling works around Fleet Marston for the viaduct;
• Piling works for the A418 overbridge
• A418 re-alignment preparatory works including piling;
• Excavation, movement and storage of earthworks;
• Several breaks from highway in the area to allow for our site access – these will include the need for some short duration traffic management;
• Continued PRoW closures in the area;
• Compound progression;
• Vegetation and site clearance
• Concreate batching plant to be operational
• Upcoming You Said, We Did for the Thame Valley Viaduct
• Preparatory works for the Stoke Mandeville Relief road.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]