HS2 Construction Works in Old Oak Common

Work item: HS2-MW-BBVS-Ph1-OOC-St-S4-CR-20-02/12/2024

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Old Oak Common lane
Worksite Name
Old Oak Common
Contractor
BBVS JV
Type of works
Electrical Works
Estimated Start Date
03/03/2025
Estimated End Date
29/05/2026

What we are doing

Electrical works are due to begin on the Old Oak Common Station site. These works will begin in June 2025, and include installing drainage, lighting and other similar activities. This will be within the HS2 Station Box and within the Conventional Station (please see the link below with map on page 2).

In preparation for these works a temporary storage area needs to be constructed on site. This will begin in March 2025. It will also serve as the central base for all electrical and mechanical works, public health, and communications work throughout the project.

Working hours
These activities are scheduled to take place from March 2025 to May 2026. Works shall only be carried out during normal working hours (Monday to Friday 8am – 6pm, Saturday 8am – 1pm).

Please see the link below for further information.

Download information relating to these works