Atlas Road closure for Thames Water weekend works
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-Works-1-29/07/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, Old Oak and North Acton
- Location
- Atlas Road
- Worksite Name
- Atlas Road
- Contractor
- SCS JV
- Type of works
- Road closure
- Estimated Start Date
- 03/08/2024
- Estimated End Date
- 05/08/2024
What we are doing
From 8am on 3 August to 8am on 5 August 2024, Thames Water will be carrying out scheduled essential works on Atlas Road.
To ensure the safety of their operatives and the local community, Atlas Road will be closed with a traffic management system in place to direct the traffic, whilst the works are being carried out.
These works are not related to any HS2 works in the area.
To support the transportation needs for the local community, SCSJV have made special arrangements that will allow buses to operate to and from the Atlas Road RATP bus depot. Buses will be permitted to take alternative routes via Channel Gate Road, our Willesden Euroterminal and Atlas Road sites and via Atlas Road. This one-way diversion will help facilitate bus movements and minimise disruptions caused by the road closure.
During these works some SCSJV lorries will temporarily be using site Gate A for access on Victoria Road. We will be using additional traffic marshals on site to help facilitate the movement and help minimise any disruption.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]