Skip to main page content
View route map

HS2: North Chilterns Area Newsletter

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-CR-47-12/07/2021

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
A413, Great Missenden
Contractor
EKFB JV
Estimated Start Date
16/12/2021
Estimated End Date
30/06/2022

What we are doing

Over the next couple of months, you can expect to see the following works in the local area;

• Ground Investigation (GI) and utility trial hole works;
• Topography surveys;
• A413 Watermain protection works south of Wendover;
• Demolition of a small bridge over the Chiltern Rail line;
• Demolition of properties on Ellesborough Road;
• Security gatehouse development work in Great Missenden;
• 12 month microbore tunnel for drainage at Great Missenden;
• Haul road progression across the area with crossing point locations in operation allowing safe vehicle access
• Excavation, movement and storage of earthworks;
• Several breaks from highway in the area to allow access for our work sites;
• Start of temporary road diversions for Nash Lee Road, Nash, Lee Lane, Ellesborough Road and Bacombe lane, Wendover ;
• Piling and preliminary works for our main structures including the Wendover Dean Viaduct and the Small Dean Viaduct;
• Clearance work and sheet piling along the network rail line.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]