Rugby Road utilities programme April 2025

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-44-01/04/2025

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
b4455
Worksite Name
Rugby Road
Estimated Start Date
06/05/2025
Estimated End Date
30/05/2025

What we are doing

As we continue works on Rugby Road to finalise the permanent road realignment. There will be a series of road closures and traffic lights, to help us complete the construction activities throughout the year. As part of the next phasing, the following activities below will be taking place.

Phase one: The removal an existing electrical cabinet, some deep excavation in the highway and the removal of approximately 70 meters of pipe, before replacements begin. The removal of the cabinet will enable a us to build a new entrance for a local business.

Phase two: Multiple utility installation. The priority is to create new ducting and connect some services under the highway. This will be carried out in several stages.

Phase three: Completion of the new business entrance after the removal of the old electrical cabinet, we will relocate the transformer power point and reconnect to the new electrical supply.

The road closure will be in place from Tuesday 6 May 2025 – Friday 30 May 2025. Traffic management will be in place 24/7.