HS2 Notification: A418 Oxford Road, crossing point update
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-04-24/03/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- A418
- Contractor
- EKFB JV
- Estimated Start Date
- 04/04/2022
- Estimated End Date
- 31/10/2022
What we are doing
In our December 2022 newsletter we updated communities on the construction of our internal site access road and crossing points.
The site access road will keep HS2 construction traffic within our work areas, helping further reduce our impact on the local community. Soon you will begin to see our construction traffic using our internal roads and temporary crossing point on the A418 Oxford Road.
This crossing point will have temporary 2-way traffic lights and is located where the A418 and our internal access road meet. The traffic lights will ensure safe, controlled crossing from our works sites across the highway. The lights for the A418 will remain on green until our construction traffic is ready to cross the highway. They will only be active during our working hours.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]