HS2 Notification: North Calvert winter update 2022

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-CR-48-11/01/2022

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Calvert
Contractor
EKFB JV
Type of works
Construction, Delivery of materials, Demolition works, Excavation works, Ground investigations, Road closure, Road realignment, Topographical surveys
Estimated Start Date
14/12/2022
Estimated End Date
30/06/2023

What we are doing

Our activity in the north Calvert area is well under way. Looking ahead over the next 3 to 6 months, you can expect to see the following works in your local area:

• Construction of the temporary diversion of Gawcott Road is due to commence in early 2023;
• Continued closure of Gawcott Road to demolish the existing bridge in early 2023;
• Delivery of abnormal loads for the Perry Hill Overbridge are planned to take place throughout winter, these deliveries will include steel beams for the bridge deck;
• Ongoing construction for the Perry Hill Overbridge abutments and wing walls;
• Throughout the winter we will be installing a pumping station to support the construction of the Perry Hill realignment works;
• We have installed 50% of the Portway culvert precast segments and plan to complete these works in spring 2023, we will also be completing in-situ elements on our Infrastructure Maintenance Depot (IMD) east and west culverts;
• Excavation and piling works to facilitate the construction of the West Street Overbridge are expected to begin in the new year;
• Localised demolition as part of our early works for the construction of bridges in the area in early 2023;
• Ground investigation, utility trial holes and topographical surveys for works in the area;
• Continued excavation, movement and storage of earthworks;
• Compound progression; and
• Wheel washers have been installed on site to help reduce mud on the local road networks this winter.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]