HS2 Notification: Notice of works, sheet piling, Small Dean Lane
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Prog-works-27-27/09/2021 1MC12-EKF-IN-NTE-CS04-000025
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Aylesbury
- Contractor
- EKFB JV
- Type of works
- Piling, Road closure
- Estimated Start Date
- 22/10/2021
- Estimated End Date
- 14/11/2021
What we are doing
As part of our continued preparatory works for the construction of the Small Dean Viaduct, we need to install sheet piles adjacent to the existing rail line near Small Dean Lane. These works are vital to protect and secure the network rail line during the construction of the viaduct over the A413.
We are planning to carry out these works over four weekends. During the works, a section of Small Dean Lane will be closed, with local diversion in place.
These works can only be done under Network Rail possession of the rail line. We will work Friday night to Sunday night, for 24 hours, over four weekends to get the work completed as quickly as possible. A section of Small Dean Lane will be closed during the weekends these works take place. The weekends these works are scheduled to take place are the following: 22nd -24th October, 29th-31st October, 5th-7th November and 12th-14th November.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]