Work Item Summary
- Project Phase
- Phase 1
- Region
- Northamptonshire
- Location
- Greatworth, Halse, Radstone
- Contractor
- Fusion JV
- Type of works
- Early construction works
- Estimated Start Date
- 02/08/2021
- Estimated End Date
- 30/09/2021
What we are doing
We have a number of preparatory activities taking place over the coming weeks ahead of the future construction of the railway. We will now be carrying out the next phase of works taking place between August and September 2021.
These activities include:
- Site welfare, laydown area, small car park establishment
- Construction of an access road alongside the copse for future works
- Site access signage