HS2 Notification: Works at Halse Copse, Halse

Work item: HS2-EW-Fusion -Ph1-Ar-Ce-C2-Prog-works-8-20/07/2021

Work Item Summary

Project Phase
Phase 1
Region
Northamptonshire
Location
Greatworth, Halse, Radstone
Contractor
Fusion JV
Type of works
Early construction works
Estimated Start Date
02/08/2021
Estimated End Date
30/09/2021

What we are doing

We have a number of preparatory activities taking place over the coming weeks ahead of the future construction of the railway. We will now be carrying out the next phase of works taking place between August and September 2021.

These activities include:

  • Site welfare, laydown area, small car park establishment
  • Construction of an access road alongside the copse for future works
  • Site access signage