Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- West Ruislip
- Contractor
- SCS JV
- Type of works
- Piling
- Estimated Start Date
- 30/11/2020
- Estimated End Date
- 31/05/2021
What we are doing
Piling works will begin in late November throughout Spring 2021 to make way for the foundations of:
o the new road bridge at Harvil Road (over the Chiltern Line and the new high speed railway)
o the new rail bridge at Breakspear Road South
o the reconstruction of the footpath bridge over the river Pinn
o the new railway embankment at West Ruislip
Download information relating to these works