HS2 Works Notification; A41 and Blackgrove Road, Fleet Marston
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Prog-works-45-08/04/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Aylesbury, Fleet Marston
- Contractor
- EKFB JV
- Type of works
- Traffic management, Vegetation clearance
- Estimated Start Date
- 15/08/2022
- Estimated End Date
- 19/08/2022
What we are doing
As part of our preparatory works, we will be carrying out localised vegetation clearance and installing a temporary fence along Blackgrove Road.
In order to carry out these additional works, we will need to extend the length of our traffic management that is currently in place for our crossing point on Blackgrove Road. For reasons of safety, there will be traffic management in the form of multi-phase lights in place for approximately 5 days.
We will be monitoring the timing of the lights as well as the traffic flow on these roads. Where practical, we will make improvements and adjustments to the lights as required.
Blackgrove Road will have additional traffic management from Monday 15 August to Friday 19 August 2022, between 8.00am and 6.00pm. There may be a short duration outside of these times to allow for the set-up of road signage and traffic lights.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]