Skip to main page content
View route map

HS2 Works Notification; A41 and Blackgrove Road, Fleet Marston

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Prog-works-45-08/04/2022

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Aylesbury, Fleet Marston
Contractor
EKFB JV
Type of works
Traffic management, Vegetation clearance
Estimated Start Date
15/08/2022
Estimated End Date
19/08/2022

What we are doing

As part of our preparatory works, we will be carrying out localised vegetation clearance and installing a temporary fence along Blackgrove Road.

In order to carry out these additional works, we will need to extend the length of our traffic management that is currently in place for our crossing point on Blackgrove Road. For reasons of safety, there will be traffic management in the form of multi-phase lights in place for approximately 5 days.

We will be monitoring the timing of the lights as well as the traffic flow on these roads. Where practical, we will make improvements and adjustments to the lights as required.

Blackgrove Road will have additional traffic management from Monday 15 August to Friday 19 August 2022, between 8.00am and 6.00pm. There may be a short duration outside of these times to allow for the set-up of road signage and traffic lights.