HS2 Works Notification: A43 and Whitfield Road, Radstone update, August 2022
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-35-08/02/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Northamptonshire
- Location
- Brackley, Radstone
- Contractor
- EKFB JV
- Type of works
- Construction, Lane closure, Road closure, Traffic management
- Estimated Start Date
- 01/04/2022
- Estimated End Date
- 06/09/2022
What we are doing
As part of our continued works for the junction upgrade, we have been working on the A43 northbound and Whitfield Road, Radstone.
Beginning in April 2022, we have been carrying out work in this area that has involved temporarily closing a section of the Whitfield Road, Radstone (the section of road between Radstone and the A43) and the A43 northbound for:
• drainage works;
• utilities connections; and
• the removal of temporary concrete barriers and narrowed lanes on the A43 northbound.
We have now carried out a road safety audit of the Whitfield Road as well as the junction upgrade where the Whitfield Road meets the A43 northbound. Now that the audit is complete, signage will be installed and the narrowed lanes will be removed.
The A43 northbound will be fully closed overnight, from the Brackley BP roundabout to the Syresham Junction, from 8.00pm Sunday 4 September to 6.00am Monday 5 September 2022 to remove the narrowed lanes that are currently in place.
Download information relating to these works