HS2 Works Notification: Abnormal load deliveries to Great Missenden

Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Prog-works-23-14/10/2022

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
A40, A413
Worksite Name
A413, Great Missenden
Contractor
EKFB JV
Estimated Start Date
07/11/2022
Estimated End Date
13/11/2022

What we are doing

As we move into the main construction phases for the bridges and viaducts in the areas of Great Missenden and Wendover, we need to start bringing in precast steel.

To reduce our impact on the local area and the amount of work taking place on site, many aspects of these bridges and viaducts will be made offsite.

As we move towards the main construction phase for the Wendover Dean Viaduct, we will start to receive deliveries of the steel beams up to 30m in length. Deliveries of this size are classed as abnormal loads.

Our haulier carried out a successful trial run in September, this has enabled us to develop the best possible method of delivery.

The abnormal loads will require short periods of temporary traffic management at four locations to complete their journey to our sites. We will also have escort vehicles in operation to support the load movement to site.

The steel deliveries will take place over the course of a week from Monday 7 November 2022. To reduce the impact on road users these deliveries will take place outside of peak traffic periods.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]