HS2 Works Notification: Break from highway update, A413 London Road

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-6-17/05/2022

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
A413
Worksite Name
A413
Contractor
EKFB JV
Type of works
Lane closure, Traffic management
Estimated Start Date
21/02/2022
Estimated End Date
31/05/2022

What we are doing

In February, we will be creating a break from highway on the A413 London Road. These works are expected to take approximately four weeks and should be finished in late March. In order to carry out these works, there will be traffic management in the form of a lane closure with two-way traffic lights.

The A413 London Road will have temporary traffic management, off peak from 9.00am to 3.30pm, commencing Monday 21 February 2022 to late April 2022.

From May, we will also be receiving the delivery of stone that will be used to construct our site access. we will remove the lane closure and install a temporary crossing point on the A413. During this time, you will see our temporary traffic lights on the crossing point switched to red for short periods of time; enabling these deliveries to safely cross the highway

Timings of work may vary due to weather and ground conditions, but we intend to work to open the roads to reduce disruption and complete the break from highway as soon as possible. Some weekend working may be required. Should there be delays to our works, these dates may be subject to change.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]