HS2 Works Notification: Brook Farm Update

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-No-Vib-42-02/10/2023

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Stoke Mandeville
Contractor
EKFB JV
Type of works
Road closure, Utility works / surveys
Estimated Start Date
30/05/2023
Estimated End Date
02/06/2023

What we are doing

As part of our preparatory works, we are planning to divert the current watermain for Brook Farm away from the HS2 line and look to
reconnect to an existing watermain along Marsh Lane.

Near Brook Farm we will continue with main works, including an open cut trench for the watermain installation. Once the work is complete, the trench will be backfilled and the ground surface reinstated.

There will be a road closure on Marsh Lane, however safe access to properties along the road will be maintained via traffic lights.

The Brook Farm utility works are anticipated to begin on Tuesday 30 May to Friday 2 June 2023.

Please note during this closure residents and their visitors may be asked about the purpose of their access through the closure.

Some of this work is subject to relevant consents and granted permissions from Buckinghamshire Council. Due to this, the dates may change due to conditions outside of our control. Please refer to the HS2 website regularly to check for any changes and updates.