HS2 Works Notification: Earthworks Update, North Portal

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Prog-works-36-21/07/2021

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Great Missenden, South Heath and The Lee, Wendover
Contractor
EKFB JV
Type of works
Construction
Estimated Start Date
02/08/2021
Estimated End Date
31/10/2021

What we are doing

Over the next few months, we will be undertaking the main earthworks in the location between the Chiltern Tunnel North Portal and Rocky Lane.

The earthworks consist of deep excavation, removal and movement of large quantities of soil between these areas in preparation to receive Align’s tunnel boring machine in 2024.

Additionally, we will be excavating the cutting for our internal haul road and the train line itself, removing and storing topsoil for the construction of our site access road.