HS2 Works Notification: Engineering works, Princes Risborough to Aylesbury railway line
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Prog-works-4-02/08/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Aylesbury
- Contractor
- EKFB JV
- Type of works
- Delivery of materials, Piling
- Estimated Start Date
- 07/03/2022
- Estimated End Date
- 31/05/2022
What we are doing
From early March, we will be carrying out some engineering work in the form of bored piling along the Princes Risborough to Aylesbury railway line. Our works will be carried out in two phases.
Phase 1
We will be carrying out these works from Monday, 7 March until early April. Works will take place between 8.00am and 8.00pm, Monday to Friday.
Phase 2
We will be carrying out these works from Friday, 8 April until mid-May. These works will take place 24-hours a day. Piling will take place outside of our core working hours but will not take place overnight. Overnight works will only include the replenishment of bentonite into our silos.
These dates may be subject to change due to weather and other circumstances outside of our control. Some additional weekend work may also take place if required.