Skip to main page content
View route map

HS2 Works Notification: Full road closure, Boddington Road

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-36-08/02/2022

Work Item Summary

Project Phase
Phase 1
Region
Northamptonshire
Location
Boddington
Contractor
EKFB JV
Type of works
Construction, Road closure, Traffic management
Estimated Start Date
12/09/2022
Estimated End Date
20/10/2022

What we are doing

As part of our work for the Banbury Road Overbridge near Lower Boddington, we will be building a new section of highway to realign Boddington Road. We are building the new road alongside the existing road, within our construction area. This means that for most of the construction period, the existing road will remain open to the public.

In preparation for this, we will be creating a temporary junction on Boddington Road. Once completed, the temporary junction will allow highway users to continue to use Boddington Road while we build the new sections of highway.

The construction of the temporary junction will take approximately 3 weeks during which a full closure of Boddington Road will be required. While this section of road is closed, we will also be building a new entrance junction for a nearby farm.

Boddington Road will be fully closed, 24 hours a day, from Monday 12 September to Thursday 20 October with a signed diversion in place.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]