HS2 Works Notification: Full road closure, Boddington Road
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-36-08/02/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Northamptonshire
- Location
- Boddington
- Contractor
- EKFB JV
- Type of works
- Construction, Road closure, Traffic management
- Estimated Start Date
- 12/09/2022
- Estimated End Date
- 20/10/2022
What we are doing
As part of our work for the Banbury Road Overbridge near Lower Boddington, we will be building a new section of highway to realign Boddington Road. We are building the new road alongside the existing road, within our construction area. This means that for most of the construction period, the existing road will remain open to the public.
In preparation for this, we will be creating a temporary junction on Boddington Road. Once completed, the temporary junction will allow highway users to continue to use Boddington Road while we build the new sections of highway.
The construction of the temporary junction will take approximately 3 weeks during which a full closure of Boddington Road will be required. While this section of road is closed, we will also be building a new entrance junction for a nearby farm.
Boddington Road will be fully closed, 24 hours a day, from Monday 12 September to Thursday 20 October with a signed diversion in place.