HS2 Works Notification: Highway improvement works on Station Road and A41 junction near Quainton
Work item: FUS_AWN_0291HS2-EW-Fusion -Ph1-Ar-Ce-C2-Traf-43-16/12/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- A41, Quainton
- Contractor
- Fusion JV
- Type of works
- Road closure, Traffic management
- Estimated Start Date
- 24/01/2022
- Estimated End Date
- 06/02/2022
What we are doing
To safely complete the junction improvement works at the A41 and Station Road and minimise daytime disruption to the A41 it is necessary to close the A41 overnight. Works are estimated to take five weekday nights to complete but are weather dependent. Due to possible weather influence a two-week period has been allocated to the work between the 24 January to the 6 February 2022 (Inclusive of weekend working).
The night closures will be between the hours of 7pm and 6am. Outside of these times and in the event of bad weather the A41 will remain open under traffic light control. A traffic diversion route will be in place (see attached map). Emergency services will be given access through the road closure.
Works that we will be undertaking during the overnight closure are:
• Plane out and remove the existing A41 road surface and replace
with new asphalt
• Installation of traffic light detector loops ahead of the future
fitting of 3-way traffic lights at the junction which will be in place
during the HS2 main construction period
• Update the carriageway line marking and road studs to include
the new Station Road filter lane on the A41
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]