HS2 Works Notification: Lane closure, Nash Lee Road and Risborough Road
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Prog-works-1-01/09/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Nash Lee, Stoke Mandeville
- Worksite Name
- Nash Lee Road
- Contractor
- EKFB JV
- Type of works
- Lane closure, Traffic management, Utility works / surveys, Vegetation clearance
- Estimated Start Date
- 30/01/2023
- Estimated End Date
- 04/02/2023
What we are doing
At Nash Lee Road we need to establish a water connection to reduce our need for water tanker deliveries.
Our utilities subcontractor, Clancy, will be connecting a spur to an existing water main on Nash Lee Road that will supply water to the compound. To complete the work, we require a lane closure and temporary traffic lights to be introduced for three days in February.
The work will involve excavating a trench for a connecting pipe to be installed into the ground adjacent to the compound. We will maintain access at all times to the residents living nearby to these works.
On Risborough Road, we will also be carrying out hedge maintenance along the entrance to Stoke House.
As these works will take place in close proximity to the road, there will be a sterile lane in place for the safety of road users and our workforce.
The Risborough Road Lane closure will take place on Monday 30 January from 09:00 – 15:00.
The Nash Lee Road lane closure will take place from Wednesday 1 – Saturday 4 February, traffic management will be in place 24 hours a day throughout these works.
These dates are subject to change due to circumstances beyond our control. Should we finish the works early, the lane closures will be removed.
Download information relating to these works