Work item: HS2-EW-Fusion -Ph1-Ar-Ce-C2-Traf-44-16/12/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Northamptonshire
- Location
- Brackley, Whitfield
- Contractor
- Fusion JV
- Type of works
- Archaeology, Lane closure
- Estimated Start Date
- 24/01/2022
- Estimated End Date
- 04/02/2022
What we are doing
As part of our continued programme of archaeological works in the local area, we are currently carrying out the next steps of our archaeological investigation work, this involves further excavation and recording any finds.
To complete the archaeology investigation in the area to the south of the A43, we need to use large plant machinery. Due to the size of the equipment required and no alternative suitable access roads available, we will need to access the site from the A43.
This will require a night-time single lane closure on the southbound A43 as you approach the Brackley BP roundabout, to enable us to carry this out safely and with minimal disruption to users of the highway.
The Whitfield village junction of The Avenue and the A43 will remain open during the lane closures for access.
The weeknight lane closures will take place between Monday 24 January to Friday 4 February 2022, 8pm and 6am.
The night operations are for localised delivery and removal works only. The archaeological investigation works will be undertaken during normal working hours.