HS2 Works Notification: Notice of road closures, Wormleighton
Work item: HS2-EW-Fusion -Ph1-Ar-Ce-C3-Traf-24-09/03/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Northamptonshire, Warwickshire
- Location
- Boddington, Chipping Warden, Lower Boddington, Priors Hardwick, Upper Boddington, Wormleighton
- Contractor
- Fusion JV
- Type of works
- Early construction works, Environmental mitigation works, Road closure
- Estimated Start Date
- 27/09/2021
- Estimated End Date
- 19/11/2021
What we are doing
Following on from the earlier completed ecology surveys we will now be continuing our established programme of bat and ecology mitigation.
To enable this to happen safely we will complete the works over eight phases of highway closures.
We will need to have daily closures, including some Saturdays, between 27 September and 19 November 2021, during the hours of 09.30am and 3.30pm (Mon – Fri) and 08.00am to 1.00pm (Sat).
This is to allow ecologists to safely observe and where necessary climb roadside trees. We will also be undertaking roadside vegetation clearance as part of the great crested newt mitigation works.
The programme, location and type of traffic management required is detailed in the notification below.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]