HS2 Works Notification: Notice of works to install additional welfare facilities at Adelaide Road
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-1-03/02/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Adelaide Road
- Worksite Name
- Adelaide Road
- Contractor
- SCS JV
- Type of works
- Construction
- Estimated Start Date
- 07/03/2022
- Estimated End Date
- 27/03/2022
What we are doing
Installation of site offices and welfare units
As part of our works to prepare for the construction of the ventilation shaft, we wrote to you last year about the installation of temporary welfare and office facilities on the eastern end of the Adelaide Road site.
However, as part of our ongoing works to set up our site, we will now be installing additional permanent site office and welfare units next to the current temporary units.
To allow the additional welfare and offices to be installed, we have removed the eastern access gate and closed this section with the site hoarding. These works are due to take place from 7 March 2022 for up
to 3 weeks.
What might you see?
There will be an increase in construction vehicles to the Adelaide Road site during these works, but we will not exceed the level of vehicles movements agreed with Camden Council.
We will use a 90-tonne crane to lift the units into site. The crane will be located on the eastern end of our site, near Beaumont Walk and Constable House.
All works will be completed within the current lane closure on Adelaide Road. No additional lane closures or traffic lights will be required.
The units will be two storeys high with a staircase on the side for access onto the first floor. A map showing the location can be found on page two.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]