HS2 Works Notification: Out of hours working, Wendover Dean Viaduct concrete pour
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Prog-works-50-11/08/2022 1MC12-EKF-IN-NTE-CS03-000049
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- A413, Wendover
- Worksite Name
- A413 Small Dean
- Contractor
- EKFB JV
- Type of works
- Cement pours, Extended working hours, Increased traffic
- Estimated Start Date
- 09/01/2023
- Estimated End Date
- 15/01/2023
What we are doing
To continue the construction of the Wendover Dean Viaduct, we will need to carry out a 22-hour concrete pour during the week commencing Monday 9 January, this is to pour the viaduct abutment.
The abutments will form the start and end of the viaduct, and they need be completed in one single pour to ensure the stability is not compromised.
As some of these works will take place overnight, there may be some noise and artificial lighting due to the nature of these works however our team will continue to monitor this.
The pour will require 640m3 of concrete, because of this there will be an increased amount of delivery vehicles visiting the Wendover Dean Viaduct work site during this pour.
To continue the works there will be more out of hours working taking place in this area in the future, we will communicate details of this in due course.
These works will take place during the day and overnight in the week commencing Monday 9 January, during the hours of 7.30am until 6:00am the following morning.
These dates may be subject to change due to circumstances outside of our control.
Download information relating to these works