HS2 Works Notification: Overnight works, Great Missenden

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-11-25/05/2022

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
A413, Great Missenden
Contractor
EKFB JV
Type of works
Road closure, Traffic management, Worksite / compound set-up
Estimated Start Date
06/06/2022
Estimated End Date
17/06/2022

What we are doing

As part of our continued preparatory works for the Wendover Dean Viaduct and other structures within the North Chilterns area, we need to adjust the carriageway layout near our Great Missenden compound.

This will include removing a section of the central reservation, and creating a straight, flat pathway through into our works compound for the abnormal load deliveries which are due to commence by the end of the year.

To allow us to do this, we need to fully close Link Road in Great Missenden overnight and introduce temporary traffic management on the A413 for approximately 2 weeks.

The link road will be fully closed overnight, from Monday 6 June to Friday 17 June 2022, between 8.00pm and 6.00am.

The A413 will have lane closures with multi-phase traffic lights beginning Monday 6 June to Friday 17 June 2022, between 8.00pm and 6.00am.

At all other times, lane 2 will be closed in each direction between Link Road and Frith Hill.

We intend to open the road fully over the weekend for all road users.