HS2 Works Notification: Overnight works, Great Missenden
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-11-25/05/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- A413, Great Missenden
- Contractor
- EKFB JV
- Type of works
- Road closure, Traffic management, Worksite / compound set-up
- Estimated Start Date
- 06/06/2022
- Estimated End Date
- 17/06/2022
What we are doing
As part of our continued preparatory works for the Wendover Dean Viaduct and other structures within the North Chilterns area, we need to adjust the carriageway layout near our Great Missenden compound.
This will include removing a section of the central reservation, and creating a straight, flat pathway through into our works compound for the abnormal load deliveries which are due to commence by the end of the year.
To allow us to do this, we need to fully close Link Road in Great Missenden overnight and introduce temporary traffic management on the A413 for approximately 2 weeks.
The link road will be fully closed overnight, from Monday 6 June to Friday 17 June 2022, between 8.00pm and 6.00am.
The A413 will have lane closures with multi-phase traffic lights beginning Monday 6 June to Friday 17 June 2022, between 8.00pm and 6.00am.
At all other times, lane 2 will be closed in each direction between Link Road and Frith Hill.
We intend to open the road fully over the weekend for all road users.