HS2 Works Notification: Overnight works, Great Missenden

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Prog-works-25-21/06/2022

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Great Missenden
Worksite Name
Great Missenden
Contractor
EKFB JV
Type of works
Enabling works, Road closure, Traffic management
Estimated Start Date
04/07/2022
Estimated End Date
15/07/2022

What we are doing

As part of our continued preparatory works for the Wendover Dean Viaduct and other structures within the North Chilterns area, we need to adjust the carriageway layout near our Great Missenden compound.

This will include removing a section of the central reservation, and creating a straight, flat pathway through into our works compound for the abnormal load deliveries which are due to commence by the end of the year.

The A413 will have lane closures with multi-phase traffic lights beginning Monday 4 July to Friday 15 July 2022, between 8.00pm and 6.00am.

The link road will be fully closed to through traffic overnight, from Monday 4 July to Friday 15 July 2022, between 8.00pm and 6.00am. However, full access will be maintained for facilities and car parks on Link Road from Great Missenden.

At all other times, lane 2 will be closed (the lane nearest to the central reservation) in each direction between Link Road and Frith Hill.

We intend to open the road fully over the weekend for all road users.

These dates may be subject to change, are dependent on weather conditions, ground conditions and other factors outside of our control.