HS2 Works Notification: Overnight works, Great Missenden
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Prog-works-25-21/06/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Great Missenden
- Worksite Name
- Great Missenden
- Contractor
- EKFB JV
- Type of works
- Enabling works, Road closure, Traffic management
- Estimated Start Date
- 04/07/2022
- Estimated End Date
- 15/07/2022
What we are doing
As part of our continued preparatory works for the Wendover Dean Viaduct and other structures within the North Chilterns area, we need to adjust the carriageway layout near our Great Missenden compound.
This will include removing a section of the central reservation, and creating a straight, flat pathway through into our works compound for the abnormal load deliveries which are due to commence by the end of the year.
The A413 will have lane closures with multi-phase traffic lights beginning Monday 4 July to Friday 15 July 2022, between 8.00pm and 6.00am.
The link road will be fully closed to through traffic overnight, from Monday 4 July to Friday 15 July 2022, between 8.00pm and 6.00am. However, full access will be maintained for facilities and car parks on Link Road from Great Missenden.
At all other times, lane 2 will be closed (the lane nearest to the central reservation) in each direction between Link Road and Frith Hill.
We intend to open the road fully over the weekend for all road users.
These dates may be subject to change, are dependent on weather conditions, ground conditions and other factors outside of our control.