HS2 Works Notification: Power cable duct installation at Drummond Street, October 2022
Work item: HS2-MW-UKPN-Ph1-Eu-St-S3-Prog-works-1-20/09/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Drummond Street
- Contractor
- UK Power Networks
- Type of works
- Cable works
- Estimated Start Date
- 05/10/2022
- Estimated End Date
- 31/10/2022
What we are doing
On behalf of HS2, UKPN are in the process of installing a new connection to the electricity network in the Camden area to reinforce their network. The work will involve digging a trench to install ducts that will then carry their power cable. This work should not have any impact on your electricity supply.
UKPN are progressing through the next sections of their works in sequenced phases. From Wednesday 5th October to 31st October, they will require a partial road closure on Drummond Street at the junction to North Gower Street down to the area before Charles Place. The traffic management set up will prevent vehicular access into Drummond Street from North Gower Street, so instead there will be a diversion to allow access onto Drummond Street from Cobourg Street, via Euston Street. Pedestrian access will not be affected.
Following these works, UKPN will be returning to complete their works at the other end of Drummond Street and will require a partial road closure from the area near the junction to Cobourg Street. More details will be available closer to the time.
Should you have any mobility issues or specific access needs or you would like any more information about these works, please do not hesitate to contact the construction manager Nick Bailey on 07850 320557 or email [email protected]
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]