HS2 Works Notification: Princes Risborough rail line
Work item: HS2-EW-EK-Ph1-Ar-No-N1-CR-34-02/09/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Type of works
- Vegetation clearance
- Estimated Start Date
- 06/03/2023
- Estimated End Date
- 26/03/2023
What we are doing
As we prepare for works later in the year along the Princes Risborough to Aylesbury (PRA) line, there are areas which we need to conduct some localised vegetation clearance and tree felling.
To complete the majority of these works we are planning on utilising the proposed Network Rail closures and completing our works while the line is closed for engineering improvement works.
Bus replacement services will be in operation throughout this period, please check the Chiltern Railways website for more information.
Other stages of clearance we will undertake during our core working hours outside of these possession times.
The daytime clearance works will take place during the week commencing 6 March and during the following weekends:
• 11-12 March 2023 – 8am-6pm
• 18 – 19 March 2023 – 8am-6pm
• 25 – 26 March 2023– 8am-6pm
Download information relating to these works