HS2 Works Notification: Princes Risborough to Aylesbury railway Update

Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Prog-works-10-19/07/2022

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Aylesbury, Princes Risborough, Stoke Mandeville
Contractor
EKFB JV
Type of works
Ground investigations, Vegetation clearance
Estimated Start Date
03/04/2022
Estimated End Date
31/08/2022

What we are doing

In early March, we began some engineering work in the form of bored piling and our works were planned to be carried out in two phases.

Phase 1

  • We began these works in early March 2022 and they are expected to be completed in May 2022. Works will take place 8.00am to 8.00pm, Monday to Friday.

Phase 2

  • We will be carrying out bored piling from late April. These works will take place 24-hours a day. Piling will take place outside of our core working hours but will not take place overnight. Overnight works will only include the replenishment of bentonite into our silos.
  • From May 2022, we will also be carrying out sheet piling. Works will take place 8.00am to 6.00pm, Monday to Friday.

These dates may be subject to change due to circumstances outside of our control and some additional weekend work may also take place if required.