HS2 Works Notification: Oatleys Road and Public Right of Way closures and diversion, Turweston
Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Prog-works-46-22/08/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Turweston
- Contractor
- EKFB JV
- Type of works
- Construction, Road closure, Road realignment, Works affecting Public Rights of Way
- Estimated Start Date
- 12/09/2022
- Estimated End Date
- 28/02/2025
What we are doing
As our part of our work for the Turweston Green Overbridge, we will need to close and divert Oatleys Road and a number of local Public Rights of Way (PRoW). These closures and diversions are required to carry out earthworks, drainage, utilities and road surfacing works between Turweston and Westbury.
We will be carrying out this work in 3 phases:
1. Closure of TUW/9/2 and TUW/5/2 during the construction of a local diversion for Oatleys Road. This work will start from 12 September 2022. TUW/9/2 will close for approx. 6 months for the diversion of Oatleys Road. TUW/5/2 will remain closed for the duration of the project until the permanent diversion has been completed.
2. Closure of Oatleys Road (TUW/4/2) to allow us to connect it into its new diversion route. This closure will be for a few days in early November. Residential access will be permitted through the work.
3. Re-opening of Oatleys Road (TUW/4/2) and TUW/9/2 with the new diversion in place. We will provide an update on the re-opening as dates are confirmed nearer the time.