HS2 Works Notification: Public Right of Way closures, Radstone
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-1-19/10/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Northamptonshire
- Location
- Radstone
- Contractor
- EKFB JV
- Type of works
- Footpath closures, Footpath diversion
- Estimated Start Date
- 15/11/2021
- Estimated End Date
- 31/01/2025
What we are doing
As part of our preparatory works and for the safety of the public, we will be closing some Public Rights of Way (PRoW), including both footpaths and bridleways in the area of Radstone.
These closures are required to support the construction of our internal site access road as well as our bulk earthworks and excavations.
Where possible, we will only close a section of a PRoW or bridleway.
Due to safety reasons as well as the programme of works, the PRoW’s will be closed in two phases.
The first phase of closures will be from November to December 2021. The PRoW’s will then be reopened until the second phase of the construction and excavation in early 2022. We will look at ways to divert the PRoW’s long term where possible.
Phase One:
Temporary closure of footpath AX15 and bridleways AX14 and AX16 in the area south of Radstone.
Works will commence Monday 15 November 2021 with a closure in place until December 2021.
Phase Two:
Closure of AX15, AX14 and AX16 from January 2022 until January 2025.
We will provide an update during the works when we are able to reopen the PRoWs where possible.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]